RoadCompletedMPRDC
Sanichara
PPP-PMPRSP Package-27(A) road rehabilitation — Pahadgadh-Sahasram corridor, completed.
Budget
₹174.70 Cr
Contract Mode
HAM
Location
Madhya Pradesh
Length
—
Start Year
2020
End Year
2023
Package
PPP-PMPRSP Package-27(A)
Progress
100%
Overview
Project Scope
Sanichara (Package-27A) covered rehabilitation and upgradation of the Pahadgadh-Sahasram road via Maran-Kanhar in Madhya Pradesh under PPP-PMPRSP. At ₹174.70 Cr on HAM basis for MPRDC, RCL delivered improved all-weather connectivity for the region.
Scope of Work
- Pahadgadh-Sahasram road via Maran-Kanhar
- Pavement rehabilitation and drainage
- HAM execution for MPRDC
Highlights
Key Facts
₹174.70 Cr — completed HAM contract
PPP-PMPRSP Package-27(A)
All-weather rural road connectivity delivered
Specifications
Technical Details
Package
PPP-PMPRSP Package-27(A)
State
Madhya Pradesh
Live Status
Completion Progress
Current completion100%
Timeline
Milestones & Progress
Project Milestones
Contract awarded
2020
Project completed
2023
Client
Project Authority
Madhya Pradesh Road Development Corp
MPRDC
Sources