RoadRunningNHAI

Hardoi Package-2A

4-lane upgradation of NH-731 — Package 2A (km 88.750 to 123.650) on Hybrid Annuity Mode.

Budget

₹564.76 Cr

Contract Mode

HAM

Location

Uttar Pradesh

Length

34.9 km

Start Year

2022

End Year

2026

Lanes

4

Highway

NH-731

Package

Package 2A

Progress

80%

Project Scope

The Hardoi Package-2A project involves improvement and upgradation of the existing NH-731 corridor to four lanes with paved shoulders over a 34.9 km stretch from km 88.750 to km 123.650 in Uttar Pradesh. Executed on Hybrid Annuity Mode (HAM), this is one of three packages forming the NH-731 four-laning program through Hardoi district.

RCL's scope includes widening existing carriageway, constructing new pavement layers, bridges, culverts, and highway furniture. HAM structure ensures NHAI annuity payments post-construction while RCL manages execution risk during the build phase.

At 80% completion, this is among RCL's most advanced active highway projects.

Scope of Work

  • 4-lane upgradation with paved shoulders — km 88.750 to 123.650
  • Existing road widening, median, and shoulder construction
  • Bridge and culvert rehabilitation and new structures
  • HAM execution — design, build, operate, maintain
  • Traffic management during construction on live highway

Key Facts

34.9 km NH-731 four-laning on Hybrid Annuity Mode

80% complete — among RCL's highest-progress active projects

₹564.76 Cr contract with NHAI

Part of multi-package NH-731 Hardoi corridor program

Improves connectivity between Lucknow and western UP

Technical Details

National Highway

NH-731

Package

Package 2A

Chainage From

88.750 km

Chainage To

123.650 km

Lanes

4

District

Hardoi

Completion Progress

Current completion80%

Milestones & Progress

Project Milestones

HAM concession agreement signed

2022

Earthwork and widening — 60% complete

2024

Pavement and structures — 80% complete

2025

Commercial operation date

2026

Progress History

20%Mar 2025

Concession agreement and mobilization

40%Jul 2025

Earthwork and carriageway widening — 40%

60%Nov 2025

Pavement layers and structures — 65%

80%Mar 2026

Current overall completion at 80%

Project Impact

34.9 km

Length

NH-731 Package 2A

80%

Progress

Near completion

Project Authority

National Highways Authority of India

NHAI