Hardoi Package-2B
4-lane upgradation of NH-731 — Package 2B (km 123.650 to 175.080) on Hybrid Annuity Mode.
Budget
₹659.87 Cr
Contract Mode
HAM
Location
Uttar Pradesh
Length
51.4 km
Start Year
2022
End Year
2026
Lanes
4
Highway
NH-731
Package
Package 2B
Progress
70%
Project Scope
Hardoi Package-2B covers the longest segment of the NH-731 four-laning program — 51.4 km from km 123.650 to km 175.080 through Hardoi district. Executed on HAM basis at ₹659.87 Cr, this project continues the corridor improvement initiated in Package 2A.
The scope includes four-lane carriageway with paved shoulders, structural works, and complete highway furniture. At 70% completion, pavement and bridge works are in advanced stages across the corridor.
Scope of Work
- 4-lane upgradation — km 123.650 to 175.080 (51.4 km)
- Continuous widening with paved shoulders and median
- Major/minor bridge construction and rehabilitation
- HAM mode execution with O&M obligations
Key Facts
51.4 km — longest NH-731 package in RCL portfolio
70% complete on ₹659.87 Cr HAM contract
Seamless continuation from Package 2A corridor
Critical link in Lucknow–western UP connectivity
Technical Details
National Highway
NH-731
Package
Package 2B
Chainage From
123.650 km
Chainage To
175.080 km
Lanes
4
Completion Progress
Milestones & Progress
Project Milestones
HAM agreement and mobilization
2022
Earthwork 50% complete
2024
Pavement and structures — 70%
2025
Commercial operation
2026
Progress History
Mobilization complete
Earthwork and widening — 45%
Structures and pavement — 60%
Current overall completion at 70%
Project Impact
51.4 km
Length
Longest NH-731 segment
Project Authority
National Highways Authority of India