RoadRunningNHAI

Kanpur Ring Road PKG-4

Six-lane greenfield ring road — Package IV (Jarkala to Pakri), southern segment of Kanpur Outer Ring Road.

Budget

₹547.67 Cr

Contract Mode

EPC

Location

Uttar Pradesh

Length

24.6 km

Start Year

2023

End Year

2027

Lanes

6

Highway

Kanpur ORR (NHDP Phase-VII)

Package

Package IV

Progress

30%

Project Scope

Package IV of the Kanpur Outer Ring Road spans 24.559 km on the southern fringes of Kanpur city, connecting Khudhgaon (Design Ch. 68.650) to Pakri/Sachendi (Design Ch. 93.209). RCL was awarded this EPC contract at ₹547.67 Cr as the lowest bidder.

This segment completes the southern arc of the 93.2 km ring, linking eastern and western parts of the city bypass. Ground levelling work has been completed and structural works are progressing across the corridor.

The six-lane access-controlled highway will integrate with NH-19 at Sachendi village, forming a complete orbital route around Kanpur.

Scope of Work

  • Six-lane greenfield from Design Ch. 68.650 to Ch. 93.209 (24.559 km)
  • Ground levelling, embankment, and pavement layers
  • Major and minor bridges, ROBs, and culverts
  • Interchanges and highway service infrastructure
  • EPC mode — design, procurement, construction turnkey

Key Facts

24.6 km southern segment of Kanpur ORR awarded to RCL at ₹547.67 Cr

Lowest bidder — significantly below NHAI's estimated cost

Ground levelling completed; structural works underway

Links Khudhgaon to Pakri, completing the southern bypass arc

Part of 93.2 km program targeting December 2027 completion

Technical Details

Highway / Program

Kanpur ORR (NHDP Phase-VII)

Package

Package IV

Chainage From

68.650 km

Chainage To

93.209 km

Lanes

6

Target Completion

December 2027

Completion Progress

Current completion30%

Milestones & Progress

Project Milestones

EPC contract awarded to RCL

Mar 2023

Ground levelling completed

2024

Structural works — 30% complete

2025

Full corridor completion

2027

Progress History

8%Mar 2025

Site mobilization and survey complete

15%Jul 2025

Ground levelling and earthwork complete

23%Nov 2025

Substructure works initiated

30%Mar 2026

Current overall completion at 30%

Project Impact

24.6 km

Length

Package IV corridor

₹547.67 Cr

Contract

EPC mode

93.2 km

ORR Program

Total ring road

Project Authority

National Highways Authority of India

NHAI