Kanpur Ring Road PKG-1

Six-lane greenfield ring road bypass — Package I (Sachendi to Mandhana), part of NHAI's Kanpur Outer Ring Road.

Budget

₹647.42 Cr

Contract Mode

EPC

Location

Uttar Pradesh

Length

23.3 km

Start Year

2023

End Year

2027

Lanes

6

Highway

Kanpur ORR (NHDP Phase-VII)

Package

Package I

Progress

50%

Project Scope

Raj Corporation Limited is constructing Package I of the Kanpur Outer Ring Road, a flagship NHAI project designed to decongest Kanpur city by providing a 93.2 km access-controlled highway around the urban core. RCL's 23.3 km segment lies west of Kanpur city, connecting Sachendi (Design Ch. 0.000) to Mandhana (Design Ch. 23.325).

The six-lane greenfield expressway is being executed on Engineering, Procurement & Construction (EPC) mode under NHDP Phase-VII. Once complete, this corridor will connect major national highways including NH-19, NH-34, and NH-27, and link to the under-construction Lucknow–Kanpur Expressway near Amarsus village.

Land acquisition for Phase 1 began in September 2021. The overall Kanpur ORR project targets completion by December 2027, with Package I targeted for opening by October 2026.

Scope of Work

  • Six-lane greenfield ring road from Design Ch. 0.000 to Ch. 23.325 (23.325 km)
  • Earthwork, pavement, bridges, culverts, and drainage works
  • Service roads, median barriers, and highway furniture
  • EPC execution including design, procurement, and construction
  • Integration with Kanpur ORR Packages 2A, 2B, 3, and 4

Key Facts

Part of ₹5,182 Cr Kanpur Outer Ring Road — India's largest urban bypass program in UP

23.3 km six-lane greenfield bypass west of Kanpur city

EPC contract awarded to RCL at ₹647.42 Cr — lowest bidder vs NHAI estimate

Connects Sachendi, Ramaipur, Rooma, and Mandhana growth corridors

Will reduce city traffic congestion by up to 40% on completion

Links to Lucknow–Kanpur Expressway at Amarsus village

Technical Details

Highway / Program

Kanpur ORR (NHDP Phase-VII)

Package

Package I

Chainage From

0.000 km

Chainage To

23.325 km

Lanes

6

Districts

Kanpur Nagar, Unnao

Target Completion

October 2026

Completion Progress

Current completion50%

Milestones & Progress

Project Milestones

NHAI tender awarded to RCL

Mar 2023

Land acquisition — Phase 1 (Ch. 0–22.5 km)

Sep 2021

Earthwork and subgrade — 50% complete

2025

Pavement and structures completion

2026

Package I opening to traffic

Oct 2026

Progress History

13%Mar 2025

Mobilization and site establishment

25%Jul 2025

Land acquisition and ROW clearance complete

38%Nov 2025

Earthwork and embankment — 50% complete

50%Mar 2026

Current overall completion at 50%

Project Impact

23.3 km

Length

Package I corridor

6

Lanes

Access-controlled greenfield

3

Districts

Kanpur Nagar, Unnao, Kanpur Dehat

93.2 km

ORR Total

Full ring road program

Project Authority

National Highways Authority of India

NHAI