RoadRunningNHAI

Moradabad PKG-2

NH-734 upgradation with Moradabad and Kashipur bypasses — Package 2, 39.8 km on EPC.

Budget

₹624.70 Cr

Contract Mode

EPC

Location

Uttar Pradesh

Length

39.8 km

Start Year

2023

End Year

2026

Lanes

4

Highway

NH-734

Package

Package 2

Progress

65%

Project Scope

Moradabad Package-2 covers improvement and upgradation of NH-734 from Moradabad to Thakurdwara, including dedicated Moradabad and Kashipur bypasses. The 39.8 km EPC contract at ₹624.70 Cr addresses chronic congestion in Moradabad city by providing alternate bypass routes.

RCL's scope includes four-lane carriageway, bypass alignments, bridge works, and complete highway infrastructure on EPC turnkey basis.

Scope of Work

  • NH-734 upgradation Moradabad to Thakurdwara — 39.8 km
  • Moradabad city bypass alignment
  • Kashipur bypass construction
  • EPC turnkey — design, procurement, construction

Key Facts

39.8 km NH-734 with dual bypasses for Moradabad and Kashipur

65% complete on ₹624.70 Cr EPC contract

Decongests Moradabad — key industrial city in western UP

Connects Delhi–Moradabad industrial corridor

Technical Details

National Highway

NH-734

Package

Package 2

Lanes

4

District

Moradabad

Completion Progress

Current completion65%

Milestones & Progress

Project Milestones

EPC contract awarded

2023

Bypass earthwork complete

2024

Main carriageway — 65%

2025

Progress History

16%Mar 2025

Site establishment

33%Jul 2025

Bypass alignment earthwork complete

49%Nov 2025

Carriageway and structures — 50%

65%Mar 2026

Current overall completion at 65%

Project Impact

2

Bypasses

Moradabad & Kashipur

Project Authority

National Highways Authority of India

NHAI